PSD/Clean Air Act: Sierra Club State Court Judicial Petition Challenging Ascension Parish Steel Mill Permit
November 24, 2026
By:
Walter G. Wright
Category:
Arkansas Environmental, Energy, and Water Law
Arkansas Environmental, Energy, and Water Law
Download PDF
Sierra Club and RISE St. James Louisiana (collectively, “Sierra Club”) filed a November 20th Petition for Judicial Review (“Petition”) in the Louisiana 19th Judicial District Court/Parish of East Baton Rouge challenging the Louisiana Department of Environmental Quality’s (“LDEQ”) granting of an extension to the commencement of construction deadline for a Clean Air Act Prevention of Significant Deterioration (“PSD”) and Part 70 Operating Permit issued to Hyundai-POSCO Louisiana Steel LLC (“HPLS”).
The Petition states that the PSD and Title V Operating Permit address HPLS’s proposed construction and operation of an integrated iron and steel production facility in Ascension Parish, Louisiana.
The Petition initially argues in part:
- The Permits would authorize the facility to emit substantial quantities of:
- Greenhouse gases
- Nitrogen oxides
- Particulate matter
- Carbon monoxide
- Lead
- Mercury
- Ammonia
- Area around the planned facility already bears a toxic air pollution burden greater than 96% of the rest of the country, and ranks high across a range of environmental and socioeconomic indicators.
Sierra Club further contends that the Permits must be vacated for the following reasons:
- LDEQ did not conduct a proper environmental justice analysis.
- LDEQ did not give full and careful consideration to mitigation measures like electrified components and green hydrogen.
- LDEQ did not assess any environmental costs in the cost-benefit analysis, nor adequately evaluate feasible pollution-reducing alternatives and mitigation measures.
- LDEQ’s Best Available Control Technology (“BACT”) analysis was issued without conducting and documenting the case-by-case analysis required for evaluating electrified technologies or incremental blending of green hydrogen.
- LDEQ’s conclusion that the HPLS plant will not cause or contribute to exceedances of the ozone National Ambient Air Quality Standards by relying on the Dutchtown neighborhood-scale ozone monitor rather than the closer Carville regional-scale monitor is incorrect.
A copy of the Petition can be found here.
The Between the Lines blog is made available by Mitchell, Williams, Selig, Gates & Woodyard, P.L.L.C. and the law firm publisher. The blog site is for educational purposes only, as well as to give general information and a general understanding of the law. This blog is not intended to provide specific legal advice. Use of this blog site does not create an attorney client relationship between you and Mitchell Williams or the blog site publisher. The Between the Lines blog site should not be used as a substitute for legal advice from a licensed professional attorney in your state.